Case studies

Delivery experience behind the advice

Selected programmes demonstrating project leadership, assurance, recovery, governance, technical integration and handover across complex capital environments.

Client and project names are withheld to protect confidentiality. Examples reflect our founder’s experience in senior client-side and consultancy roles.

Illustrative diagram of a radiotherapy treatment vault structural and equipment interface, not the actual facility
Sector
Healthcare
Project
Specialist radiotherapy treatment centre, NHS teaching hospital
Founder's role
Client-side Project Manager
Capability
Programme recovery / integration assurance
Context
A highly complex clinical and technical programme combining deep basement construction with specialist high-energy treatment equipment procured directly by the NHS trust.
What was done
Challenged an unrealistic construction programme, drove resequencing and NEC-compliant milestones, and managed interfaces where equipment tolerances and radiation-protection requirements were critical.
Outcome / relevance
Programme was recovered to an agreed handover position while maintaining commercial engagement and protecting the integration path.
Illustrative diagram of the interface between a live clinical estate and an active construction zone, not the actual facility
Sector
Healthcare
Project
Major cancer centre, acute teaching hospital
Founder's role
Client-side Project Manager
Capability
Delivery assurance / stakeholder integration
Context
A major cancer treatment facility delivered within a live healthcare estate with legacy-information gaps, service tie-ins and third-party tenant requirements.
What was done
Coordinated clinical, FM, contractor and tenant interfaces; managed design-development/change tensions; protected operational requirements and programme.
Outcome / relevance
Facility opened on time and within budget.
Illustrative diagram of a governance reset and two-stage design and build procurement route, not the actual programme
Sector
Healthcare
Project
Specialist hospital relocation programme
Founder's role
Client-side project lead
Capability
Governance setup / procurement
Context
A major healthcare relocation programme inherited after an extended design competition, with weak governance, limited programme definition and misaligned stakeholder groups.
What was done
Established the PEP and governance structure, clarified information flows, assessed the design team and led two-stage design-and-build procurement through preferred-contractor selection.
Outcome / relevance
Created a controlled delivery platform ready for mobilisation.
Illustrative diagram of nested vibration, EM and thermal isolation envelopes for a precision measurement laboratory, not the actual facility
Sector
Science & Research
Project
Government research laboratory — high-sensitivity measurement facility
Founder's role
Project leadership
Capability
Technical delivery / recovery
Context
High-sensitivity measurement facilities with demanding vibration, infrasound and electromagnetic-isolation performance and international specialist interfaces.
What was done
Rebuilt design-team capability, coordinated specialist requirements, managed client leadership changes and contractor/commercial challenges through delivery.
Outcome / relevance
Required performance was achieved at handover for highly sensitive scientific use.
Illustrative mockup of the S&S recovery action tracker showing live-estate coordination actions
Sector
Public Estate
Project
Government department estate programme, including a flagship low-carbon office
Founder's role
Project Manager
Capability
Delivery recovery / live-estate coordination
Context
Complex government estate projects involving refurbishment, new build, decant, live operations, incomplete legacy information and changing phasing constraints.
What was done
Managed re-phasing, access, planning, FM interfaces, design gaps and soft-landings issues while maintaining delivery controls.
Outcome / relevance
The flagship office was completed on time and within the original budget, achieving BREEAM Excellent on completion and later BREEAM Outstanding, the scheme’s highest rating.
Illustrative mockup of the S&S findings register tool showing RAG-rated issues
Sector
Life Sciences
Project
Global pharmaceutical R&D / laboratory programme
Founder's role
Independent PMO / assurance adviser
Capability
Programme assurance / governance
Context
A complex laboratory fit-out requiring stronger governance, controls and client-side assurance through design, procurement, construction and handover.
What was done
Developed project controls, PEP/governance, change and risk controls, programme acceptance, technical decision routes and handover/operational-readiness oversight.
Outcome / relevance
Created a structured control environment and independent challenge around programme, technical decisions and readiness.
Illustrative diagram of a data centre commissioning test-level sequence from component testing to handover, not the actual programme
Sector
Data Centres
Project
Live data-centre commissioning & close-out
Founder's role
Project / programme assurance
Capability
Commissioning readiness / close-out
Context
Fast-moving live data-centre delivery with system testing, commissioning dependencies and handover dates requiring transparent weekly control.
What was done
Built activity trackers, critical-path and slippage reviews, testing/witnessing controls, close-out reporting and commissioning readiness views.
Outcome / relevance
Improved visibility of prerequisites, incomplete works, sequencing conflicts and handover risk.

Relevant experience